Update - The replacement part is due to arrive within 5 to 7 days. This means the cooling in HHS2 should be operations by Monday 3 February.
Jan 20, 2025 - 12:26 AEDT
Update - We are continuing to work on a fix for this issue.
Nov 08, 2024 - 09:16 AEDT
Identified - Heating and Cooling services in LaTrobe Rural Health School (LRHS) have been interrupted due to unscheduled maintenance works. We aim to have these services back online as soon as possible.
Nov 08, 2024 - 09:15 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 20, 2025 - 07:00 AEDT
Scheduled - Biological Sciences 2 (128, 136, 218, 225, 226, 315 and 322) will be undergoing building fabrics works. The estimated time of completion is Thursday 26 January 2025. This project may generate some construction noise during this time.
Jan 20, 202507:00 - Jan 24, 202500:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 13, 2025 - 09:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Jan 13, 202509:00 - Feb 28, 202516:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Jan 13, 202509:00 - Feb 28, 202516:00 AEDT
Scheduled - The Library, Social Sciences, David Myers West, LaTrobe Institute for Molecular Science 1 and The Learning Commons Buildings will be undergoing Balustrade upgrade. The estimated time of completion is Friday 28 Feb 25. This project may generate some construction noise during this time.
Jan 13, 202509:00 - Feb 28, 202516:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 13, 2025 - 08:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Jan 13, 202508:00 - Mar 2, 202516:00 AEDT
Scheduled - The Library, Social Sciences, Martin, Biological Sciences 1 & 2, LaTrobe Institute for Molecular Science 1 and The Learning Commons Buildings are currently undergoing construction works around the elevated walkways surrounding the library. Walkway will have restricted access; project may generate some construction noise during this time. Estimated time of completion is 2 Mar 2025.
Jan 13, 202508:00 - Mar 2, 202516:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 06, 2025 - 08:00 AEDT
Scheduled - Education 2 will be undergoing building fabric alterations. The estimated time of completion is Tuesday 25 February 2025. These works will generate noise which will travel to ED1, SW and HU2.
Jan 6, 202508:00 - Feb 25, 202516:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 06, 2025 - 07:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Jan 6, 202507:00 - Feb 7, 202515:30 AEDT
Scheduled - The Library, Social Sciences and Martin Buildings will be undergoing Excavation works. The estimated time of completion is Friday 7 Feb 2025. This project may generate some construction noise during this time.
Jan 6, 202507:00 - Feb 7, 202515:30 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Dec 23, 2024 - 08:00 AEDT
Scheduled - Access to ED1 Level 4 will be unavailable from Monday 23 December 2024 until Sunday 9 February 2025 to allow for scheduled maintenance works. Heating and cooling will also be switched off as a result.
Dec 23, 202408:00 - Feb 9, 202517:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Dec 23, 2024 - 08:00 AEDT
Scheduled - The heating and cooling to ED1 Level 4 will not be running from Monday 23 December 2024 until Sunday 9 February 2025 and staff are encouraged to work from a different location during this time.
Dec 23, 202408:00 - Feb 9, 202517:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Dec 02, 2024 - 14:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Dec 2, 202414:00 - Jan 24, 202517:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Dec 2, 202414:00 - Jan 24, 202517:00 AEDT
Scheduled - Access to Car Park 2 from Kingsbury Drive will be closed on Tuesday 2 Dec 24 from 2pm to Friday 24 Jan 25 at 5pm for scheduled maintenance works.
Dec 2, 202414:00 - Jan 24, 202517:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Nov 29, 2024 - 11:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Nov 29, 202411:00 - Mar 17, 202515:00 AEDT
Scheduled - Education 2 Level 2 is currently undergoing building fabric and project works. The estimated time of completion is Monday 31 Mar 25. This project may generate some construction noise during this time.
Nov 29, 202411:00 - Mar 17, 202515:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Nov 25, 2024 - 07:30 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Nov 25, 202407:30 - Mar 31, 202515:00 AEDT
Scheduled - LIMS1 forecourt area is currently undergoing Building Fabric and Project works including refurbishment of the Hoogenraad Lecture Theatre. The estimated time of completion is 31 March 2025. This project may generate some construction noise during this time.
Nov 25, 202407:30 - Mar 31, 202515:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Nov 25, 2024 - 07:00 AEDT
Scheduled - David Myers East is currently undergoing roof replacement to ensure long-term building integrity. The estimated time of completion is Friday 28 February 2025.
Construction Impacts:
Noise: Expect ongoing drilling noise throughout the construction period. Heating and cooling: There will be no heating and cooling to Level 2 of DME. Building access: There will be some temporary impacts to building access from the Level 2 link bridges while scaffolding is erected during site establishment.
Nov 25, 202407:00 - Feb 28, 202515:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Nov 18, 2024 - 07:00 AEDT
Scheduled - The linkway joining levels 2 and 3 of Humanities 2 and Humanities 3 buildings will be going structural repairs. The estimated time of completion is Friday 24 January 2025. This project may generate some construction noise during this time.
Please note the roadway will not be accessible from the Sylvia Walton boom gate to the Perebolis East car parks. Parking will not be available in this area during the construction period.
Nov 18, 202407:00 - Jan 24, 202515:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Oct 28, 2024 - 08:00 AEDT
Scheduled - Teaching and Learning Spaces TLC-155, PW-215 and PW-217 will be transformed to create an immersive and rich learning experience for La Trobe Students and encourage industry-based learning and collaboration with an expected completion date of Monday 3 March 2025. Construction noise may be heard at times.
Please note works will cease during exam time.
Oct 28, 202408:00 - Mar 3, 202517:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Oct 28, 2024 - 08:00 AEDT
Scheduled - Teaching and Learning Spaces BUS-130, BUS-228, BUS-229 and BUS-230 will be transformed to create an immersive and rich learning experience for La Trobe Students and encourage industry-based learning and collaboration with an expected completion date of Monday 3 March 2025. Construction noise may be heard at times.
Please note works will cease during exam time.
Oct 28, 202408:00 - Mar 3, 202517:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 16, 2025 - 11:24 AEDT
Scheduled -
The power supply to The University Lodge- Building A, Mont Park Building B, La Trobe Apartments North, La Trobe Apartments South will be interrupted on Tuesday 21 Jan 25 from 7:00am - 10am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 16, 2025 - 11:24 AEDT
Chisholm College (Block 1 1CST1, Block 4 4BS1 and Block 8 8CST1)will be undergoing building fabrics works. The estimated time of completion is Friday 24 January 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:32 AEDT
Education 1 (Room 112) will be undergoing building fabrics works. The estimated time of completion is Friday 24 January 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:45 AEDT
David Myers East (room 185) will be undergoing building fabrics works. The estimated time of completion is Friday 24 January 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:35 AEDT
Biological Sciences 2 (475) will be undergoing building fabrics works. The estimated time of completion is Friday 24 January 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:28 AEDT
The Union Building (Rooms 118 - East Side and 337) will be undergoing building fabrics works. The estimated time of completion is Wednesday 29 January 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:57 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 17, 2025 - 14:14 AEDT
Scheduled -
Animal House will be undergoing brief fabrics works. The estimated time of completion is Friday 31 Jan 25. This project may generate some construction noise during this time.
Jan 17, 2025 - 14:14 AEDT
MC-NW (Rooms 164 and 166) will be undergoing building fabrics works. The estimated time of completion is Monday 3 February 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:55 AEDT
GC-AD (111) will be undergoing building fabrics works. The estimated time of completion is Tuesday 4 February 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:49 AEDT
MC-DH (1ST2) will be undergoing building fabrics works. The estimated time of completion is Tuesday 4 February 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:53 AEDT
Education 2 (Rooms 116 and 117) will be undergoing building fabrics works. The estimated time of completion is Wednesday 5 February 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:48 AEDT
Biological Sciences 2 (124,251, 353 & 461) will be undergoing building fabrics works. The estimated time of completion is Wednesday 5 February 2025. This project may generate some construction noise during this time. Posted on
Jan 17, 2025 - 15:27 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 17, 2025 - 14:16 AEDT
Scheduled -
Agora Theatre will be undergoing building fabrics works. The estimated time of completion is Thursday 6 Feb 25. This project may generate some construction noise during this time.
Jan 17, 2025 - 14:16 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 17, 16:01 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 16, 07:01 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 15, 14:42 AEDT
Scheduled -
Heating services in the Learning Commons will be unavailable on Thursday 16 Jan 25 from 7:00AM - 4:00PM Friday 17 Jan 25 to allow for scheduled maintenance works.
Jan 15, 14:42 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 17, 16:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 17, 07:01 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 15, 14:32 AEDT
Scheduled -
The power supply to Landscaping Building, Lower Playing Field Pavilion, Physical Sciences 2 Building, LifeSkills, Sports Park Pavilion will be interrupted on Friday 17 Jan 25 from 7am - 4pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 15, 14:32 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 17, 08:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 17, 07:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 15, 14:20 AEDT
Scheduled -
The power supply to Campus Services Buildings 1,2,2A will be interrupted on Friday 17 Jan 25 from 7am to 8am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 15, 14:19 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 16, 17:30 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 16, 08:00 AEDT
Scheduled -
Scheduled maintenance testing of the fire and essential safety measures systems (both wet and dry) is taking place across campus on Thursday 16 January 2025 between 08:00am and 4:30pm. Tones may sound during this time.
Jan 10, 15:26 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 16, 16:01 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 16, 07:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 13, 09:10 AEDT
Scheduled -
Scheduled annual maintenance testing of Pump and essential safety measures systems is taking place Campus wide on Thursday 16 Jan 25 from 7:00am - 4:00pm. Tones may sound during this time.
Jan 13, 09:09 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 16, 16:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 16, 07:00 AEDT
Scheduled -
The power supply to George Singer, Indoor Sports Centre, Sylvia Walton and the Zoology Reserve will be interrupted on Thursday 16 January 2025 between 07:00am and 4:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 9, 13:57 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 16, 09:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 16, 08:00 AEDT
Scheduled -
The power supply to John Scott Meeting House will be interrupted on Thursday 16 January 2025 between 08:00am and 09:00am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 9, 13:56 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 16, 08:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 16, 07:01 AEDT
Scheduled -
The power supply to Jenny Graves will be interrupted on Thursday 16 January 2025 from 07:00am - 08:00am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 9, 14:54 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 15, 16:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 15, 07:00 AEDT
Scheduled -
The power supply to Agora East, Agora West, Agora Theatre, Boiler House, David Myers East, Central and West, Eastern Lecture Theatre and the Wildlife Sanctuary will be intermittently interrupted on Wednesday 15 January 2025 between 07:00am and 4:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 9, 13:52 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 15, 08:30 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 15, 06:00 AEDT
Scheduled -
The power supply to the Library will be intermittently interrupted on Wednesday 15 January 2025 between 06:00am and 08:30am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 9, 13:40 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 14, 16:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 14, 07:00 AEDT
Scheduled -
The power supply to Biological Sciences 1, Education 1, Education 2, Health Sciences 1, Health Sciences 2, Health Sciences 3, Health Science Clinic, Western Lecture Theatre, NR1, NR2, NR3&4, NR6, NR7, NR8, Peribolos East, Peribolos West, Physical Sciences 2, Sports Park Pavillion, Union and La Trobe Lifeskills will be intermittently interrupted on Tuesday 14 January 2025 from 07:00am to 4:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 9, 13:35 AEDT