In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 04, 2026 - 10:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Feb 4, 202610:00-15:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Feb 4, 202610:00-15:00 AEDT
Scheduled - The power supply to The Learning Commons building will be interrupted on Wednesday 4 Feb 26 from 10:00am - 3:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Feb 4, 202610:00-15:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 02, 2026 - 08:00 AEDT
Update - We will be undergoing scheduled maintenance during this time.
Feb 2, 202608:00 - Feb 5, 202617:00 AEDT
Scheduled - The Library and Student Union building on level 3 - South End staff offices, will be undergoing plumbing works. The estimated date of completion is Thursday 5 Feb 26. The plumbing works will generate some noise; staff may wish to avoid working in this area during this time.
Feb 2, 202608:00 - Feb 5, 202617:00 AEDT
Update - We are continuing to work on a fix for this issue.
Jan 28, 2026 - 14:11 AEDT
Identified - Air-conditioning services in Menzies College Dining Hall level 2 Rooms 201, 201a & 202 have been interrupted due to unscheduled maintenance works. We aim to have these services back online as soon as possible.
Jan 28, 2026 - 14:11 AEDT
Identified - Air-conditioning services in Health Science 2, Meeting room 440 and offices 441, 443, 444, 445, 446 and 447 have been interrupted due to unscheduled maintenance works. We aim to have these services back online as soon as possible.
Jan 27, 2026 - 13:25 AEDT
Identified - Air-conditioning services in ED have been interrupted due to unscheduled maintenance works. We aim to have these services back online by 3:30pm Wednesday 28 January.
Jan 27, 2026 - 10:04 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Nov 18, 2025 - 07:00 AEDT
Scheduled - Donald Whitehead Building, Physical Sciences 1, R.L.Reid Building and The Learning Commons will be undergoing Lift Upgrades starting 7am Tuesday 18th November 2025. The estimated time of completion is 3:00pm Friday 20th February 2026. This project may generate some construction noise during this time.
Nov 18, 202507:00 - Feb 20, 202615:00 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Nov 17, 2025 - 08:28 AEDT
Scheduled - Amenities across levels 2, 3 and 4 of Humanities 3 will be undergoing refurbishment. The estimated time of completion is Friday 20th March 2026. This project may generate some construction noise during this time.
Nov 17, 202508:28 - Mar 20, 202616:28 AEDT
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Nov 10, 2025 - 07:00 AEDT
Scheduled - The amenities areas on Level 2, Level 3 and the internal stairwell (all levels) of the Education Building will be undergoing refurbishment. The estimated time of completion is Thursday 12th March 2026. This project may generate some construction noise during this time.
Nov 10, 202507:00 - Mar 12, 202615:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 14:34 AEDT
Scheduled -
The power supply to the George Singer building will be interrupted on Thursday 5 Feb 26 from 6:00am - 9:00am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 2026 - 14:34 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 30, 2026 - 12:27 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 30, 2026 - 12:26 AEDT
Scheduled -
Scheduled maintenance testing of the fire and essential safety measures systems is taking place Campus wide on Thursday 5 Feb 26 from 8:00am - 4:00pm. Tones may sound during this time.
Jan 30, 2026 - 12:26 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 14:43 AEDT
Scheduled -
The power supply to Western Lecture Theatre will be interrupted on Thursday 5 Feb 26 from 9:00am - 12:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 2026 - 14:43 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 14:36 AEDT
Scheduled -
The power supply to Union building will be interrupted on Thursday 5 Feb 26 from 9:00am - 3:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 2026 - 14:36 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 14:39 AEDT
Scheduled -
The power supply to the Lifeskills Building will be interrupted on Thursday 5 Feb 26 from12:00pm - 12:30pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 2026 - 14:39 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Feb 02, 2026 - 12:54 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Feb 02, 2026 - 12:52 AEDT
Scheduled -
Scheduled maintenance testing of the fire and essential safety measures systems is taking place in the Hillside Apartments 1-6 on Friday 6 Feb 26 from 7:00am - 5:00pm. Tones may sound during this time.
Feb 02, 2026 - 12:52 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 14:48 AEDT
Scheduled -
The power supply to Ernest Jones Hall, The University Lodge- Building A, Mont Park Building B, Mont Park Building C and Mont Park Building D will be interrupted on Friday 6 Feb 26 from 7:00am - 3:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 2026 - 14:48 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 15:09 AEDT
Scheduled -
The power supply to Mont Park Building E will be interrupted on Friday 6 Feb 26 from 7:00am - 9:00am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 2026 - 15:09 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 15:06 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 14:56 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 14:54 AEDT
Scheduled -
The power supply to Ernest Jones Hall will be interrupted on Friday 6 Feb 26 from 9:00am - 10:00am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 2026 - 14:54 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 2026 - 15:18 AEDT
Scheduled -
The power supply to Health Sciences 1, 2 & 3 will be interrupted on Saturday 7 Feb 26 from 7:00am - 3:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 2026 - 15:18 AEDT
The power supply to Donald Whitehead and Martin Building will be interrupted on MONDAY 9 FEBRUARY between 7:00AM and 3:00PM to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested. Posted on
Feb 03, 2026 - 10:28 AEDT
The power supply to ISC POOL/GYM will be interrupted on WEDNESDAY 10 FEBRUARY between 06:00AM and 07:00AM to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested. Posted on
Feb 03, 2026 - 10:31 AEDT
The power supply to ISC (OFFICES) and JSM will be interrupted on WEDNESDAY 10 FEBRUARY between 07:00AM and 08:00AM to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested. Posted on
Feb 03, 2026 - 10:36 AEDT
The power supply to MT, NR1 ,NR2 , NR 6,NR 8 , SS, Z will be interrupted on TUESDAY 10 FEBRUARY from 08:00AM to 3:00PM to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested. Posted on
Feb 03, 2026 - 10:59 AEDT
The power supply to LTWS will be interrupted on TUESDAY 10 FEBRUARY from 08:00AM to 09:00AM to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested. Posted on
Feb 03, 2026 - 10:56 AEDT
Completed -
The scheduled maintenance has been completed.
Feb 4, 10:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 4, 07:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 13:30 AEDT
Scheduled -
The power supply to R.L.Reid Building will be interrupted on Wednesday 4 Feb 26 from 7:00am - 10:00am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 13:30 AEDT
Completed -
The scheduled maintenance has been completed.
Feb 3, 15:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 3, 11:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 13:27 AEDT
Scheduled -
The power supply to Education 2 and Humanities 3 buildings will be interrupted on Tuesday 3 Feb 26 from 11:00am - 3:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 13:27 AEDT
Completed -
The scheduled maintenance has been completed.
Feb 3, 11:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 3, 07:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 13:24 AEDT
Scheduled -
The power supply to Education 1 and Humanities 2 buildings will be interrupted on Tuesday 3 Feb 26 from 7:00am - 11:00am to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 13:24 AEDT
Completed -
The scheduled maintenance has been completed.
Feb 3, 08:30 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 3, 07:30 AEDT
Scheduled -
The power supply to LIMS1 (LEVEL 7 PLANT ROOM) will be interrupted on TUESDAY 3 FEBURARY from 7:30AM to 8:30AM to allow for scheduled maintenance works.
Feb 2, 10:44 AEDT
Completed -
The scheduled maintenance has been completed.
Feb 3, 08:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 3, 07:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Feb 2, 11:45 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Feb 2, 11:44 AEDT
Scheduled -
The power supply to Glenn College South Wing Levels 1,2,3 will be interrupted on Tuesday 3 Feb 26 from 7:00am - 8:00am to allow for Residual Current Device (RCD) changeover.
Feb 2, 11:44 AEDT
Completed -
The scheduled maintenance has been completed.
Feb 2, 15:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Feb 2, 07:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 13:21 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 27, 13:20 AEDT
Scheduled -
The power supply to Beth Gleeson and Sylvia Walton will be interrupted on Monday 2 Feb 2026 from 7:00am to 3:00pm to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 27, 13:20 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 31, 08:30 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 31, 08:00 AEDT
Scheduled -
The power supply to Peribolos West room 121 will be interrupted on Saturday 31st January from 08:00am until 08:30am to allow for scheduled maintenance works.
Jan 30, 11:58 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 30, 16:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 30, 09:00 AEDT
Scheduled -
The power supply to LPFP, SPP, AFL LIGHT POLES and NR8 will be interrupted on FRIDAY 30 JANUARY BETWEEN 9:00AM AND 4:00PM to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 23, 09:57 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 30, 09:01 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 30, 06:00 AEDT
Scheduled -
The power supply to LTSS will be interrupted on FRIDAY 30 JANUARY BETWEEN 6:00AM AND 9:00AM to allow for Residual Current Device (RCD) / safety switch testing. These works will incur a minor power outage for up to 10 seconds on each circuit tested.
Jan 23, 09:37 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 30, 06:30 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 30, 05:00 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 29, 13:47 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 29, 13:02 AEDT
Scheduled -
The power supply to MC-RES, MCA, MC-NW, MC-SW, MC-DH & MC-AD will be interrupted on Friday 30 Jan 26 from 5:00am - 6:30am to allow for scheduled maintenance works.
Jan 29, 13:02 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 29, 09:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 29, 08:00 AEDT
Scheduled -
The power supply to HS1 DB1.1 will be interrupted on Thursday 29th January 2026 from 7:00am to 8:00am to allow for scheduled maintenance works.
Jan 28, 07:55 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 23, 17:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 16, 08:00 AEDT
Scheduled -
Scheduled annual maintenance testing of the fire and essential safety measures systems is taking place in the ARTS and LSU buildings from 08:00AM FRIDAY 16 JANUARY to 5:00PM FRIDAY 23 JANUARY. Tones may sound during this time.
Jan 14, 10:49 AEDT
Resolved -
This incident has been resolved.
Jan 23, 16:33 AEDT
Monitoring -
Air-conditioning services in Donald Whitehead and Martin Building have been interrupted due to unscheduled maintenance works. We aim to have these services back online as soon as possible.
Jan 21, 14:36 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 23, 16:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 19, 06:00 AEDT
Scheduled -
Scheduled maintenance testing of the fire and essential safety measures systems is taking place in L, ISC, SPP, PS1, PS2, MAR, MC Annex from 06:00 MONDAY 19 JANUARY until 4:00PM FRIDAY 23 JANUARY. Tones may sound during this time.
Jan 14, 12:29 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 22, 16:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 22, 08:00 AEDT
Scheduled -
Heating and/or Cooling services in the Education building will be offline on THURSDAY 22nd JANUARY between 08:00am AND 4:00pm due to mechanical upgrades.
Jan 21, 14:01 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 21, 18:05 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 14, 09:05 AEDT
Update -
We will be undergoing scheduled maintenance during this time.
Jan 14, 09:03 AEDT
Scheduled -
The Health 1 Nursing & Midwifery level 2 will be undergoing refurbishment project works. Noise works and access may impact CSC, GDP, HHS2 and VA. Alternative Access between HHS2 and LSU is through VA. The estimated date of completion is Wednesday 21st January 2026. This project may generate some construction noise during this time.
Jan 14, 09:03 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 21, 07:30 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 21, 07:01 AEDT
Scheduled -
The power supply to RLR level 2 will be interrupted on WEDNESDAY 21 JANUARY BETWEEN 7:00AM AND 730AM to allow for scheduled maintenance works.
Jan 20, 11:11 AEDT
Completed -
The scheduled maintenance has been completed.
Jan 21, 07:00 AEDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 21, 06:30 AEDT
Scheduled -
The power supply to RLR level 1 will be interrupted on WEDNESDAY 21 JANUARY BETWEEN 6:30AM AND 7:00AM to allow for scheduled maintenance works.
Jan 20, 11:07 AEDT