PROJECT WORKS - JG [BUNDOORA]

Scheduled Maintenance Report for LTU | Outages

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 12, 2025 - 00:00 AEDT

Scheduled

Level 3 of Jenny Graves will be undergoing an upgrade of the gas detection system within the PC2 facility. The estimated time of completion is Tuesday 15th April.

Please note that during the duration of the upgrade works, some access doors and corridors may be cordoned off. After works have been completed, testing will take place which may activate the audible and visual alarms.
Posted Feb 26, 2025 - 12:36 AEDT
This scheduled maintenance affects: Melbourne (Bundoora) Campus Buildings (JG | Jenny Graves Building).