POWER OUTAGE - TER7 EMA EMB EMC [BUNDOORA]
Scheduled Maintenance Report for LTU | Outages
Completed
University Lodge- Building A, Mont Park Building B&C and Terrace 7 have been rescheduled from Friday 19th February and will now be completed between 7:00 am and 4:00 pm Wednesday 3rd February.
Posted Jan 20, 2021 - 14:45 AEDT
Scheduled
The power supply to The University Lodge- Building A, Mont Park Building B&C and Terrace 7 will be interrupted from 07:00 am to 4:00 pm Friday 19th February to allow for annual RCD Push Button Testing. These works will incur a minor power outage for up to 10 seconds on each circuit that’s being tested. Power will be restored once each circuit has been tested (10 second outage).
Posted Jan 14, 2021 - 11:39 AEDT
This scheduled maintenance affected: Melbourne (Bundoora) Campus Buildings (EMA | The University Lodge- Building A, EMB | Mont Park Building B, EMC | Mont Park Building C, TER 7 | Terrace 7).