POWER OUTAGE - TER9 TER10 TER11 TER12 TER13 TER14 [BUNDOORA]
Scheduled Maintenance Report for LTU | Outages
Completed
The power supply to Terraces 9-14 have been rescheduled from Thursday 18th February and will now be completed between 7:00 am and 4:00 pm Friday 5th February
Posted Jan 20, 2021 - 15:07 AEDT
Scheduled
The power supply to Terraces 9-14 will be interrupted from 07:00 am to 4:00 pm Thursday 18th February to allow for annual RCD Push Button Testing. These works will incur a minor power outage for up to 10 seconds on each circuit that’s being tested. Power will be restored once each circuit has been tested (10 second outage).
Posted Jan 14, 2021 - 11:32 AEDT
This scheduled maintenance affected: Melbourne (Bundoora) Campus Buildings (TER 9 | Terrace 9, TER 10 | Terrace 10, TER 11 | Terrace 11, TER 12 | Terrace 12, TER 13 | Terrace 13, TER 14 | Terrace 14).