Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 04, 2021 - 11:27 AEDT
Update
Week of 4th Oct- deliver/store glass and aluminium and remove blinds and move desks etc in arts rooms Week of 11th Oct- remove and replace windows on arts building Week of 18th Oct- arts windows and some windows on library and stairwell Week of 1st Nov- setup scaffold for Big windows on library and remove blinds etc on library windows (TBC) Week of 8th until finished- Library windows and possibly arts windows over garden bed area
Posted Oct 04, 2021 - 11:27 AEDT
Scheduled
Arts and Library and Student Union are currently undergoing maintenance works. The estimated date of completion is 5:00 pm Tuesday 30th November. This project may generate some construction noise during this time.
Posted Oct 04, 2021 - 11:26 AEDT
This scheduled maintenance affected: Bendigo Campus Buildings (ARTS | Arts, LSU | Library and Student Union).