SYSTEM INTERFACE TESTING - MH1, MH2 [ALBURY WODONGA]
Scheduled Maintenance Report for LTU | Outages
Completed
The scheduled maintenance has been completed.
Posted Dec 07, 2021 - 10:00 AEDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 07, 2021 - 08:00 AEDT
Update
 MH1 – 8.00am to 9am
 MH2 – 9am to 10am
Posted Nov 30, 2021 - 13:49 AEDT
Scheduled
Infrastructure and Operations will be undertaking routine System Interface Testing of McFarlanes Hill Residence 1 and McFarlanes Hill Residence 2 between 08:00 am and 10:00 am Tuesday 7th December. Testing will involve activating a smoke detector to generate an alarm on the building FIP to test the system operates as it should in a fire. There will be evacuation tones and the system will impact heating and cooling.
Posted Nov 30, 2021 - 13:49 AEDT
This scheduled maintenance affected: Albury Wodonga Campus Buildings (MH1 - McFarlanes Hill Residence 1, MH2 - McFarlanes Hill Residence 2).