POWER OUTAGE - PE PW [BUNDOORA]
Scheduled Maintenance Report for LTU | Outages
Completed
The scheduled maintenance has been completed.
Posted Jan 18, 2021 - 16:00 AEDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 18, 2021 - 07:00 AEDT
Scheduled
The power supply to Peribolos East & West (DATA CENTRE will not be affected) will be interrupted from 07:00am to 4:00 pm Monday 18th January to allow for annual RCD Push Button Testing. These works will incur a minor power outage for up to 10 seconds on each circuit that’s being tested. Power will be restored once each circuit has been tested (10 second outage).
Posted Jan 13, 2021 - 11:29 AEDT
This scheduled maintenance affected: Melbourne (Bundoora) Campus Buildings (PE | Peribolos East, PW | Peribolos West).